INTEG BOQ

PROJECT : MRT - 7 PROJECT
LOCATION : QUEZON CITY TO SAN JOSE DEL MONTE, BULACAN
CLIENT :SAN MIGUEL CORP.
SUMMARY OF QUANTITIES FOR DETAILED ENGINEERING DESIGN (DED)
MRT7
ITEM NO.DESCRIPTIONUNITQUANTITYUNIT COST (Pesos)AMOUNT (Pesos)REMARKS
INTEGRATION, AND TESTING AND COMMISSIONING OF MRT-7 STATIONS AND DEPOT ELECTRONICS NETWORKS
Phase 1 (Stations to Depot-Admin Bldg- OCC Integration)
Fire Detection and Alarm System (FDAS) Workstation Computer System (1123.2.8)
Complete with the following:
Workstation Computer (1123.2.8.A*) To use 32"' LED Monitor
Server (for centralized FDAS management) (1123.2.8.B*)
Software** (1123.2.8.C*)
Network Switch (1123.2.8.D*)
Uninterruptible Power Supply (UPS) (1123.2.8.E*)
Peripherals (1123.2.8.E*)
*Please refer Engineering Specification (Electronics) for Depot for the specific and other requirements requirements.
** Monitoring and Control Software, including graphical user interface shall have a perpertual license.
Lot1.00
Access Control System (ACS) Workstation Computer System (1124.2.6)
Complete with the following:
Server Computer (1124.2.7*)
L2 (Layer 2) Switch with SFP (Small Form-Factor Pluggable) Ports (1124.2.8*)
Badge Printer (1124.2.12*)
System Software **(1124.2.13*)
System Database (1124.2.14*)
*Please refer Engineering Specification (Electronics) for Depot for the specific and other requirements requirements.
** Monitoring and Control Software, including graphical user interface shall have a perpertual license.
Lot1.00
Supply and installation of required network interface card and or other required media converter and gateways including software’s for the system integration.ps1.00
Supply and installation of Control and Communication Cable including related accessories to complete the systemps1.00
Supply and installation of Power Supply Cables including Conduit and Boxes and other related accessories to complete the systemps1.00
Table and Chairs for Admin-OCCps1.00
Testing and commissioningLot1.00
Phase 2 (Depot Buildings to Depot Admin Bldg-FCCR Integration)
Supply and installation of Control and Communication Cable including related accessories to complete the systemLot1.00
Supply and installation of required network interface card and or other required media converter and gateways including software’s for the system integration.ps1.00
Supply and installation of Power Supply Cables including Conduit and Boxes and other related accessories to complete the systemLot1.00
Table and Chairs for Admin-FCCRps1.00
Testing and CommissioningLot1.00